Information from NHS Surrey and Sussex
Latest progress
Following enabling works at the end of last year and the start of the main construction in
January, the overall build for the new Weybridge health facility is progressing well and is on
target for completion by autumn 2027.
Currently, the main shell of the building is complete, with window installation and roof works
now progressing. The next stage will see roofing and external windows and doors
completed, underfloor heating installed, with internal partition walls starting to go up.
Overall, the project is on target for completion of the building by April 2027 (Phase 1), with the
Phoenix Practice expected to move in from next April.
Phase II – laying out and completion of the car park – will then follow, with the full project
expected to be completed by mid-October 2027.
Surrey County Council Highways will be undertaking Highways Improvement Work, which
includes Church Street, with timings to be confirmed.
About the new facility
The new Health Facility will deliver a modern, integrated range of health and wellbeing
services tailored to the local population needs. It will include:
• A permanent home for the Phoenix Family Practice
• Maternity care
• Same-day urgent care
• Diagnostic services
• Flexible clinical and community space to support evolving service delivery
This development supports the ambitions of the NHS Long Term Plan, bringing care closer
to home and enabling more sustainable, neighbourhood-based services for Weybridge and
surrounding areas.